Con la fase de perforación finalizada, el consorcio detrás del proyecto geotérmico de 20-60 MW en Batangas, Filipinas, inicia fase de testeo de pozos para determinar el potencial posible para la planta geotérmica planificada.

(PiensaGeotermia en “modo vacaciones”)

The consortium of Basic Energy, Phinma Energy just announced having concluded drilling on site of its Mabini geothermal project in Batangas, Philippines.

The companies are now conducting tests that are to determine the resources output for the project. With the drilling the companies have now fulfilled a DOE commitment for its geothermal service contract no.8. The drilling reached the target depth of 1,679 meters and preparations are under way to set perforated liners.

“Testing of the well aimed at obtaining temperature, pressure, and permeability data, to be performed by its contractor, Scientific Drilling International (SDI), shall commence shortly,” the firm said.

According to the Senior VP and General Manager of Basic Energy, Anthony Cuaycong, completion tests will last three days are provide sufficient data to determine the actual resource potential for the project.

“After the completion test, there is a heat-up period of up to one and a half months, during which time surveys will be conducted to check well response after specific ‘rest’ periods,” Cuaycong said.

Pre-feasibility studies show that Service Contract no. 8, which covers 3, 841 hectares, can yield between 20 to 60 megawatts of power.